Completion of the Library Refurbishment Project

We are pleased to inform all stakeholders of the completion of the SU Library Refurbishment Project. Construction work began in February 2021 and was completed at the beginning of May 2022. The handover of all the spaces to the Library was officially done on 13 May 2022. Save for some snagging, the project is now complete.

The project ran in three overlapping phases:

Phase 1 of the project consisted of renovations of the client service desk, short loans and related staff work areas and staff toilets as well as the refurbishment of lower-level toilets.

Phase 2 of the project entailed work in the central section of the upper level that involved the installation of new student study and work areas, and the completion of new flooring.

Phase 3 comprised the renovation of the entrance foyer, access control and new security area and the installation of the adjacent reading area as well as new work desks for students along the double volume space.

We would like to thank all clients for demonstrating high levels of tolerance, understanding and patience during these refurbishments. Disruptive as they were, these renovations have ensured that clients have access to comfortable and effective spaces that befit a world class Library in a world class research-intensive University.

For further details contact Delene Pretorius.